Norway · Statnett datacenter queue · free public view

Grid queue intelligence

Every datacenter and AI-compute application moving through Statnett milestones — live.

Applications

167

Active queue

11.7 GW

Applicants

114

Substations

70

Recent moves
NPG HOLDING AS30 MWQueued Aug 2026
HÅBAKKEN NÆRINGSPARK AS4 MWQueued Aug 2026
MAGNORA ASA50 MWQueued Jul 2026
HAUKEVEIEN HOLDING AS90 MWQueued Jul 2026
FJORDCORE ÅLESUND AS20 MWQueued Jul 2026
FISKUMPARKEN C4 AS350 MWQueued Jun 2026
SI OSL 04 AS0 MWReserved Jun 2026
MAGNORA ASA95 MWQueued Jun 2026

Application milestone timeline

Datacenter queue

Rows1-100 / 167
Sort
MarkersAppliedReservedQueuedPlanned connectionConnected
Applicant·Station
2018202020222024202620282030203220342036
MW

Queued

25/02791 · Datacenter

MW

8mo

Reserved

22/00602 · Datacenter

MW

4y 4mo

Queued

24/01801 · Datacenter

MW

1y 9mo

Queued

25/02364 · Datacenter

MW

10mo

Reserved

25/01925 · Datacenter

MW

1y 7mo

Queued

24/01473 · Datacenter

MW

2y 4mo

Queued

26/03896 · Datacenter

MW

4mo

Reserved

24/01882 · Datacenter

MW

1y 8mo

Reserved

21/00289 · Datacenter

MW

7y 7mo

Reserved

23/01257 · Datacenter

MW

2y 9mo

Queued

25/02293 · Datacenter

MW

11mo

Queued

25/02362 · Datacenter

MW

10mo

Reserved

21/00233 · Datacenter

MW

8y 2mo

Queued

26/03504 · Datacenter

MW

5mo

Queued

24/01822 · Datacenter

MW

1y 9mo

Queued

25/02153 · Datacenter

MW

1y 2mo

Connected

21/00015 · Datacenter

180/180MW

<1mo

Queued

24/01661 · Datacenter

MW

2y 4mo

Reserved

24/01807 · Datacenter

MW

1y 9mo

Queued

25/02663 · Datacenter

MW

9mo

Queued

25/02389 · Datacenter

MW

10mo

Reserved

24/01805 · Datacenter

MW

1y 9mo

Queued

24/01806 · Datacenter

MW

1y 9mo

Withdrawn

21/00193 · Datacenter

144MW

<1mo

Reserved

23/01250 · Datacenter

MW

2y 9mo

Queued

25/02625 · Datacenter

MW

9mo

Queued

26/03693 · Datacenter

MW

5mo

Queued

25/02405 · Datacenter

MW

10mo

Queued

25/02609 · Datacenter

MW

9mo

Queued

25/01967 · Datacenter

MW

1y 6mo

Queued

24/01901 · Datacenter

MW

1y 8mo

Connected

21/00082 · Datacenter

110/110MW

<1mo

Reserved

24/01774 · Datacenter

MW

4y 7mo

Reserved

23/01030 · Datacenter

MW

3y 2mo

Queued

25/02232 · Datacenter

MW

2y 5mo

Queued

24/01758 · Datacenter

MW

1y 11mo

Queued

24/01769 · Datacenter

MW

1y 11mo

Queued

25/02700 · Datacenter

MW

8mo

Queued

26/03802 · Datacenter

MW

4mo

Queued

26/04105 · Datacenter

MW

3mo

Queued

26/03415 · Datacenter

MW

6mo

Queued

26/03165 · Datacenter

MW

6mo

Queued

26/03402 · Datacenter

MW

6mo

Queued

26/03099 · Datacenter

MW

7mo

Queued

26/04512 · Datacenter

MW

1mo

Queued

26/04019 · Datacenter

MW

4mo

Queued

26/03524 · Datacenter

MW

5mo

Queued

26/03096 · Datacenter

MW

7mo

Queued

25/02154 · Datacenter

MW

1y 2mo

Queued

25/01983 · Datacenter

MW

1y 6mo

Queued

26/03170 · Datacenter

MW

6mo

Queued

25/02231 · Datacenter

MW

1y

Queued

25/02600 · Datacenter

MW

9mo

Reserved

21/00212 · Datacenter

MW

6y 4mo

Queued

25/03020 · Datacenter

MW

7mo

Queued

25/01920 · Datacenter

MW

1y 9mo

Reserved

25/02112 · Datacenter

MW

3y 10mo

Reserved

21/00460 · Datacenter

MW

4y 9mo

Queued

25/02560 · Datacenter

MW

9mo

Reserved

21/00298 · Datacenter

MW

8y 6mo

Queued

25/02032 · Datacenter

MW

1y 6mo

Queued

25/02160 · Datacenter

MW

1y 1mo

Queued

26/04080 · Datacenter

MW

3mo

Reserved

24/01660 · Datacenter

MW

2y 3mo

Reserved

23/01192 · Datacenter

MW

2y 10mo

Reserved

23/01400 · Datacenter

MW

2y 8mo

Reserved

24/01770 · Datacenter

MW

1y 11mo

Queued

26/03395 · Datacenter

MW

6mo

Queued

26/03529 · Datacenter

MW

5mo

Queued

26/03306 · Datacenter

MW

6mo

Queued

26/03846 · Datacenter

MW

4mo

Queued

26/03432 · Datacenter

MW

6mo

Queued

25/03021 · Datacenter

MW

7mo

Queued

25/02698 · Datacenter

MW

8mo

Queued

25/02124 · Datacenter

MW

1y 2mo

Reserved

24/01503 · Datacenter

MW

2y 6mo

Reserved

24/01555 · Datacenter

MW

2y 5mo

Queued

25/03004 · Datacenter

MW

7mo

Queued

25/02605 · Datacenter

MW

9mo

Queued

25/02545 · Datacenter

MW

9mo

Queued

24/01911 · Datacenter

MW

1y 7mo

Connected

21/00070 · Datacenter

40/40MW

<1mo

Connected

21/00270 · Datacenter

40/40MW

<1mo

Connected

21/00035 · Datacenter

37/37MW

<1mo

Reserved

24/01504 · Datacenter

MW

2y 6mo

Reserved

24/01869 · Datacenter

MW

1y 8mo

Connected

24/01597 · Datacenter

33/33MW

<1mo

Reserved

23/01372 · Datacenter

MW

2y 8mo

Reserved

24/01894 · Datacenter

MW

2y 6mo

Reserved

23/00956 · Datacenter

MW

3y 5mo

Reserved

22/00665 · Datacenter

MW

4y

Reserved

21/00206 · Datacenter

MW

6y 4mo

Queued

25/02719 · Datacenter

MW

8mo

Queued

26/03976 · Datacenter

MW

4mo

Withdrawn

22/00693 · Datacenter

30MW

<1mo

Connected

21/00179 · Datacenter

30/30MW

<1mo

Reserved

23/01062 · Datacenter

MW

3y

Queued

25/02068 · Datacenter

MW

1y 4mo

Queued

24/01833 · Datacenter

MW

1y 9mo

Queued

23/00951 · Datacenter

MW

3y 3mo

Showing 1–100 of 167
Page 1 of 2

Station cartography

Substations and queue pressure

Queue accumulation

Applications over time

Cumulative requested capacity from the current Statnett snapshot, reconstructed across time from milestone dates and split by each row's lifecycle stage at the selected month.

Active + connected
12.3 GW
Applications
167
In queue
8.4 GW
As of
Aug 2026
036912152020202220242026GW cumulative

Lifecycle

167 applications · 12.3 GW active or connected capacity (11.7 GW active queue, 641 MW connected). 189 MW withdrawn is shown as removed capacity and excluded from that total. Five lifecycle buckets, ordered left-to-right by Statnett milestone. Rows inside each bucket are Statnett source statuses scoped to that lifecycle bucket.

5 lifecycle buckets · 7 source-status groups
  1. No rows in the current datacenter scope.

Live datacenter scope

Statnett publishes a single national connection queue covering generation, storage, industrial load, and datacenter applications. This page filters that queue to rows where Statnett's own industry classification is datacenter — 167 rows out of the 937 rows in the full Statnett source pull. MW totals below are summed within those datacenter rows; they are not netted against generation, storage, or other load in the broader queue.

Statnett dataset change · June 2026

In late June 2026, alongside stricter project-maturity rules that took effect 1 July, Statnett restructured its public connection dataset. It now publishes cases in only three states — in queue, reserved, and connected — and has temporarily dropped cases still under assessment (projects being evaluated for maturity before they secure a place in the queue). Statnett says it is improving the data foundation and aims to publish all active cases again in the autumn. This page mirrors what Statnett publishes, so the assessment stage is not shown for now — it will reappear here when Statnett restores it.

Methodology

The grid map for European datacenter siting

Power is now the constraint.

Substralis is the source-backed grid map for teams siting compute, storage, and industrial load in Europe. We turn scattered TSO publications into one operating picture, with the source trail next to every number.

01

Every number has a receipt.

Source, timestamp, and a link back to the original publication travel with every value, so your analysis holds up when someone checks it.

02

History, not just today.

Queues move through stages. We keep every change, so yesterday's portal refresh becomes a record you can query — not a screenshot you lost.

03

Faithful to each source.

Headroom, queues, and markets are published in different shapes. We preserve those differences instead of flattening them into a false average.